Worldwide Shipping Fast Technical Quote zaferguney@duso.com.tr

On-site production

Production Where the Project Needs It.

Production machines are shipped to the project site. Steel may be supplied from Türkiye, or suitable local steel may be used subject to technical requirements. Supervisor support, setup and operator training complete the mobilisation.

01 On-Site Production

Production where the project needs it.

Production machines are shipped to the project site. Steel may be supplied from Türkiye, or suitable local steel may be used subject to technical requirements. Supervisor support, setup and operator training complete the mobilisation.

Obra a gran escala en condiciones invernales
01

Mobilisation

Equipment, steel coil and documentation prepared for the destination site.

02

Installation

Machine setup, alignment and commissioning on the project layout.

03

Training

Operator briefing on forming, corrugation and basic quality checks.

04

Production

On-site duct manufacturing matched to programme and logistics.

05

Technical Support

Supervisor support for process stability and spare-part readiness.

02 Process

Complete on-site solution

  1. 01

    Project Requirement Analysis

    Sizes, thicknesses, programme, site constraints and steel origin are defined.

  2. 02

    Machine Configuration

    Tooling and line configuration are matched to the required duct range.

  3. 03

    Machine Mobilization

    Equipment is prepared, shipped and received at the project location.

  4. 04

    Steel Supply

    Coil is sourced from Türkiye and/or qualified local supply.

  5. 05

    Installation & Training

    Line is commissioned; operators and supervisors are trained.

  6. 06

    On-Site Production

    Duct is produced to the project schedule under the agreed control plan.

Machinery photography placeholder

03 Production Machines

When on-site production is considered

  1. 01

    High metreage with constrained logistics

  2. 02

    Remote or restricted import conditions

  3. 03

    Programme that favours continuous local production

  4. 04

    Need to align duct output with tendon installation rate

Request a Quote

Discuss Your On-Site Production Requirement

Share your technical requirements with our team.